Since your teams started using AI, has velocity gone up? More points can look like proof that AI and agile are working well together. Think of a car on ice: the wheels can spin faster while the car stays put. In a sprint, a short planning period, velocity adds up the estimated points for work the team finished. It does not tell you how much reached users. Count what reached them alongside velocity, then investigate where the two measures diverge.

What the data shows

In its July 2025 report, Faros AI, a vendor of engineering measurement software, analysed records from more than 10,000 developers across 1,255 teams. For each team it compared quarters of lower and higher AI use. In the higher-use quarters, teams averaged 21% more tasks completed per developer and 98% more pull requests merged per developer. A pull request is a proposed code change; merging incorporates it into the shared code. In that comparison, median review time rose by about 91%. The report suggests reading the delivery results directionally: it found no significant correlation between AI adoption and improvement at the company level in the number of items finished, delivery measures or quality.

This is one vendor’s observational report, with weak correlations between these measures and AI use. It cannot establish that AI caused the differences, or that delivery stood still. That gap between what was measured at team and company level is worth checking in your own teams.

Why velocity was never a productivity measure

Velocity helps a team plan its next sprint. Story points are a team’s own estimates of the size of work. Comparing two teams’ totals is like comparing two currencies with no exchange rate. The trouble starts when velocity becomes a target. Nicole Forsgren and colleagues’ SPACE framework for developer productivity gives the example of a team rated only on story points: it would tend to optimise its own points, at the expense of invisible work that others depend on, such as helping a colleague. That is an illustration of the framework’s warning, not a finding from data.

The social scientist Donald Campbell described the wider pattern. The more a number is used to make decisions, the more pressure it attracts, and the more it can bend the very work it was meant to observe.

Why AI and agile velocity can drift apart

Now add AI. If AI makes some coding tasks quicker, teams may finish more tickets or take on more work. Writing code is only one step, though. Review, testing and release come after it, and any of them can become the place where work waits. The Faros report links part of its longer lead time for change, measured from a pull request to production, to longer review cycles. It treats that as a directional signal, and its figures can’t tell you where work waits in your teams.

A second case shows what a target can miss. In June 2025, the chief technology officer of a mid-sized software company set a goal of doubling merged pull requests per engineer. Hao He and colleagues studied that company in a preprint on arXiv, which has not been peer reviewed. Adoption was not random. The researchers looked at changes after developers adopted AI, relative to colleagues whose use did not change in the same months. Among the active developers in their analysis, the average monthly count of authored pull requests rose from 21.2 to 44.3 between the January to April 2025 baseline and April 2026. The episode uses the rounded figures when discussing merged pull requests. In the paper, they count authored requests and do not show whether the company met its merge target.

The pool of developers acting as reviewers grew only 1.5 times, while the load per reviewer roughly doubled as measured by pull requests per reviewer. Among non-bot pull requests in the analysis sample, the share receiving a human-written review comment fell from about 39% to about 21%. A comment is a stand-in for review depth, not proof of quality. None of this showed up in the number the company was watching, the count of merged pull requests. The authors describe the site as unusually favourable for AI and treat their result as an upper bound rather than an industry average.

Not a people problem

Velocity can rise even when people estimate honestly. If you reward higher totals, teams have a reason to spend more time on work that earns points and less on work the measure misses, such as helping another team. A higher total can also reflect a change in the mix of work.

When introducing AI in agile delivery, follow the work through review, testing and release. Flow is how work moves from start to finish, including where it waits.

What to put beside velocity

Keep velocity for planning the next sprint. Put a count of delivered items beside it. John Coleman and Daniel Vacanti’s The Kanban Guide (edition 2025.5, CC BY-SA 4.0) defines throughput as “the number of work items finished per unit of time”, and notes that it is an exact count (initial letter lowercased here). The guide leaves the finish point to the team. For this comparison, count an item once it is available to its intended users, inside or outside the organisation.

Read the delivery count and velocity together. Each pattern gives you a question:

  • Velocity up, throughput up: the extra work may be landing. Check that the items are comparable before you celebrate.
  • Velocity up, throughput flat: worth a look. Sizing may have shifted, the mix of items may have changed, releases may have slipped, or work may be waiting.
  • Velocity flat, throughput up: the team may be splitting work into smaller items, or finishing what it started. Worth asking which.
  • Both flat: the counts show no change. Has the size, value or quality of the work changed?

Imagine a team that goes from 40 points a sprint to 55 over three sprints after adopting AI tools, while it still finishes about a dozen items a sprint. (This is an illustrative example, not a real team.) The estimated points total is about 38% higher. The throughput count shows no change in items. The useful conversation starts there: which of those explanations fits?

The count has limits. It is sensitive to how items are split, and it says little by itself about quality or customer value. If you are rolling out AI for agile teams across several departments, compare each team with its own past, not with the others. The guide to checking AI developer productivity in your own team covers cycle time, how long finished work took, and work item age, how long work still in progress has been under way. The guide to DORA delivery measures explains how to check whether releases needed urgent fixes.

How you’ll know it’s working

Choose one team this week. Agree what counts as reaching users. Compare two recent equal periods using release records, and check that the work was actually available to the people it was meant for. If the counts diverge, trace one item and test a possible explanation. If they move together, check whether the team changed how it splits work. Bring one finding or open question to the next review. The count is useful if it helps the team decide what to inspect or change.